This presentation describes the replacement and bypass of the Cell Import/Export Manifolds and 10" Cell Fill Lines located in the Utility Shaft of the Brent Bravo platform. The construction activity installed a new Import/Export Manifold at EL +87m, above the existing equipment at the Cell Fill Manifold level.
The conversion from existing to replacement Cell Fill Lines required the isolation and removal/replacement of the relevant existing Cell Fill Lines. A general description of the work area and its location was provided, with a brief introduction to the function of the main systems contained within the Utility Leg.